Project Component

 

The project has 12 components, which comprises of a set of sub-components and activities as listed below.

 

Component Major Sub-Component Major Work component
Preparatory Work Survey and mapping of project area Approximately 7,023 km2 (forest land: 4,357 km2)
Demarcation of JFM area 400 hamlets/groups of hamlets
Socio-economic baseline survey 500 hamlets/groups of hamlets (400 hamlets/groups of hamlets+ 100 control hamlets for the comparison of cases with and without project)
Strengthening of Implementing Organization Construction of PMU / NTFP Centre of Excellence building 4500 m2
Construction of DMU buildings 2,000 m2 (250 m2 x 8 DMUs)
Construction of RMU buildings 4,500 m2 (150 m2 x 30 RMUs)
Construction of residential quarters (DMU) 1,600 m2 (200 m2 x 8 DMUs)
Construction of residential quarters (RMU) 3,600 m2 (120 m2 x 30 RMUs)
Vehicles 4WD x 6 (PMU), 4WD x 24 (DMU and RMU), Motorcycle x 66 (RMU)
Training for Implementing Organization Analysis of  Training needs Trainings, Study tours, Annual review seminars etc.

6,500 person days

 

Special Forest resource augmentation A R- 300 ha , Bamboo and cane -400 ha), ANR*-1,300 ha