|
|
|
Minutes of Meetings
Minutes of the review meeting
chaired by the Chief Executive Officer & Project Director,
Tripura JICA Project in his office chamber at Aranya Bhavan,
Agartala on the 7th January, 2009.
A meeting was convened by the CEO and Project Director, Tripura
JICA Project to review the progress of work of the Project
Management Consultants ( the list of participants is appended)
on the 7th January, 09 to discuss and finalize the following
issues and the resolutions emerged in the meeting are mentioned
below:
GIS
During discussion GIS Specialist highlighted the critical &
pending issues relating to project area mapping that require
immediate action. There was detailed discussion on restriction
in use of Survey of India Topographical maps and ways and means
to prepare of Project Area Maps in absence of such maps. The PMU
requested the PMC members to elaborate the road map of
alternative options/ methodologies available as inputs for GIS
database creation.
The following decisions emerged in the meeting on the
preparation of project area maps.
1. Review of Bids for Project Area Mapping: It was decided that
Technical Committee would be analysing the bids on 8th Jan 2009
and would be deciding the next course of action.
2. Computer Hardware: The procurement of required desktop
computers and server has been approved by PMU. It was decided to
follow-up the matter and expedite the process.
3. Computer Software: The procurement of required software along
with GIS software has been approved by PMU. It was decided to
follow-up the matter and expedite the process.
4. Technical Staff from TSAC on deputation: The two Engineers/
Scientists from TSAC were assigned to the project on part-time
basis from 7th Jan 2009 for imparting training to Forest
officials. Since the requirement of the project is of two
Engineers/ Scientists from TSAC on full-time basis to assist
JICA project in creation of GIS database, therefore, this needs
to be discussed and clarified to TSAC/Department of Science &
Technology. PMU has decided to clarify again to TSAC about the
actual requirement and the job description of the deputed staff
from TSAC.
IGA
1. It was agreed that induction training of the newly appointed
Livelihood Coordinators (40 in number) would be held at Prajna
Bhavan from January 19 to 24, 2009.
2. The action plan for imparting training to the LCs was
finalized.
3. The letters of invitation to identified resource persons
would be prepared and dispatched on January 9, 2009.
Survey and Mapping
It was informed by the PMC that two Teams of the Surveyors from
the Working Plan Division-I are likely to complete the survey
work in North and Gomati Forest Divisions soon. But, the three
Teams of the Surveyors from the Working Plan Division-II are yet
to be deployed in the field for the survey and mapping work. One
team went to the field for two days and then came back. The PMU
has to take immediate action in this regard.
MIS
The PMC members explained the concerns for timely submission of
MIS datasheets by all DMUs. Till date only one DMU (Kailasahar)
has submitted the filled in MIS datasheets – it was submitted on
4th December, 2008. The datasheets are yet to come even after
one and half months’ of agreed timeline for submission. PMU
agreed to follow-up with all DMUs to send the MIS Datasheets
immediate. It was informed that the Notification/ Advertisement
for the recruitment of MIS Analyst has already been sent for
insertion in the newspapers and it is likely to appear soon. MIS
Analyst shall be engaged for updation of the MIS information
among others.
NCE activities
On the subjects of formulation of State NTFP policy, modalities
of assessment of bamboo resources, and entering into
correspondence with prospective organisations identified for van
mela etc, which Director, NCE desires from the PMC members were
discussed but it was decided that the issue shall be discussed
with the Director NCE. It was also decided that PMU shall take
decision as to what all is expected from CTA and PMC members and
whether there are resources for the new activities.
Status report on the Project
The Project Director/CEO requested the PMC members GC to prepare
a status report on the Project activities for FY 2009-10. This
would help in understanding the present status and further works
required to be done. The PMC members based on the information
available with the PMU would prepare a status report and share
it with PMU. The process should start at JFMC level to discuss
about the next year’s activities and then the RMU has to prepare
its annual plan of operation based on the activities to be
undertaken in different JFMCs and also other measures to be
taken up at the RMU level. Once the DMU gets all the Plan of
Operation from the RMUs it shall prepare the overall Annual Plan
of Operation. A meeting of all Project Managers and Foresters/BOs
needs to be organized at the DMU level to finalize the Annual
Plan of Operation of the DMU for 2009-10 and also the Annual
Status Report of the Project for 2008-9. The process shall be
taken up during January – February 2009 so that the PMU could
come up with its Annual Plan of Operation in March 2009.
The meeting was concluded thanking everybody present
Appendix
|
PMU |
Project Management Consultants |
|
Sh. S . Talukdar, CEO & PD
Sh.P. Biswas, Director (A&F) |
Dr.Manoj Pattanaik
Dr Ram Prasad
Sh. Shalabh P. Bharadwaj
Ms Varsha Mehta
Sh. Anurag Gupta |
|